Geotechnical Engineering Service ListingA partial list of relevant Project experience for TBT Engineering and/or its staff is as follows: Island Drive Bridge, Thunder Bay, ON:Cook Engineering Ltd.At 234 m, the Island Drive Bridge is the longest integral abutment bridge in Canada. This project involved detailed field investigations (both on and off shore), extensive geotechnical laboratory analyses and advanced geotechnical modeling. Key foundation design issues included:
Building Settlement Evaluation, Terry Fox Elementary School, Ottawa, ON:IRC Batten Sears Group Inc.Geotechnical engineering assessment of building settlements. Various possibilities of the reported settlements were investigated and included, long term consolidation, ground loss, frost heave, changes in moisture content, and bearing capacity. Two primary causes of settlements were identified for separate sections of the school. Slope instability of a 6 m high creek valley slope was identified as the root cause for settlements along one section of the school, while consolidation from tree roots below the foundations was identified as a source of settlement at another location. Through detailed slope stability analyses of the slope, it was determined that extensive slope re-grading and removal of some port-a-pack classroom additions would be the most feasible remediation option.
Impacts on Trunk Sewer from Proposed Commercial Development, Thunder Bay, ON:OPUSThe proposed commercial development involved a significant raise in grade and the construction of several commercial buildings adjacent an existing trunk sewer buried at a depth of approximately 10 m. Given the compressible nature of the clay soils on site and large loads from the proposed construction, stresses and settlement induced onto the sewer were of concern. This assessment determined there was significant risk to the sewer in terms of hydraulic and structural integrity. Alternate foundation types and various modifications to site grading (including lightweight fills) were developed to mitigate these risks.
Highway Embankment Failure, Hwy 11 South of Polly Lake Road:Ministry of Transportation
Geotechnical investigation for stabilization recommendations for an embankment failure which occurred on the west side of Highway 11, approximately 100 m south of Polly Lake Road. The failed embankment (approximately 8 m high) partially filled in an existing creek located near the toe of the embankment. Scope of work for this project was to assess slope stability and provide comparative costs for various remedial options. Key geotechnical tasks and issues included:
Moosonee Water and Wastewater Design Build Project, Moosonee, ON:Reid Crowther and Partners
Geotechnical investigation and design recommendations for the construction of a water treatment plant with associated reservoir, a low raw water pump system, sewage lagoon, sewage pumping stations, forcemain and watermains. Key geotechnical tasks and issues included:
Bridge Approach Grading, Eleanor Bay and Big Grassy River Bridges, Morson, ON:McCormick Rankin Corporation
Geotechnical investigations for bridge approach grading for two bridges. The existing approaches were to be raised by 1 to 2 m. The approaches were situated over existing causeways, which were underlain by soft clays. To facilitate construction of the grade raise while maintaining embankment stability and improving settlement performance various geotechnical treatments were designed and evaluated. Extensive consolidation and strength testing of the foundation soils were required for detailed design. Key geotechnical tasks and issues included:
Construction Impacts on Segmental Sewer, Famous Players Theatre, Thunder Bay, ON:Tom Jones Corporation Inc.Geotechnical assessment and recommendations for a piled foundation, grade raise and impacts of construction on a near by buried segmental sanitary trunk sewer. Project involved the prediction of construction effects (including piling operations) on the adjacent sewer. Later, a series of test piles were driven to confirm pile capacity and to optimize the design with respect to potential construction effects on the sewer. During driving a test piles an extensive monitoring program was implemented to measure vibrations, ground movements, sewer deflections, and porewater pressure generation in the surrounding soils. In addition, visual inspections of the sewer were carried out. Based on the results of the monitoring program, it was determined that the planned piling operations would not pose any significant risk to the sewer.
"From Testing Through to Consultation,
|
Recent Projects
-
Projects Coming Soon






